Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 169: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Project Number:
Title:
Upper Columbia Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 20.00%
Methow 40.00%
Wenatchee 40.00%
Contract Number:
56662 REL 169
Contract Title:
2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Contract Continuation:
Previous: Next:
56662 REL 142: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
  • 56662 REL 200: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
This contract will fund the Yakama Nation's Upper Columbia Habitat Restoration Project to seek, design and implement fish habitat restoration projects throughout the Methow, Entiat, and Wenatchee subbasins for the FY 2019 performance period.  Administrative tasks related to this SOW, such as reporting and inventory management, are provided under BPA Contract 56662 REL 161.
Account Type(s):
Expense
Contract Start Date:
10/01/2018
Contract End Date:
12/31/2019
Current Contract Value:
$1,744,521
Expenditures:
$1,744,521

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes No Technical Contact adas@yakamafish-nsn.gov (509) 945-0754
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Jason Breidert Yakama Confederated Tribes Yes Technical Contact brej@yakamafish-nsn.gov (509) 860-5351
Chris Butler Yakama Confederated Tribes Yes Technical Contact butlerc@yakamafish-nsn.gov (509) 449-8215
Christopher Clemons Yakama Confederated Tribes Yes Technical Contact clec@yakamafish-nsn.gov (509) 881-5746
Annet Dillman Yakama Confederated Tribes No Administrative Contact dila@yakamafish-nsn.gov (509) 865-2255
Madeleine Eckmann Yakama Confederated Tribes Yes Supervisor eckm@yakamafish-nsn.gov (509) 449-2091
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Jarred Johnson Yakama Confederated Tribes Yes Supervisor johj@yakamafish-nsn.gov (509) 881-1462
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Timothy Ludington Bonneville Power Administration Yes COR tsludington@bpa.gov (503) 230-4988
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Steve Parker Yakama Confederated Tribes No Interested Party pars@yakamafish-nsn.gov (509) 865-6262x6342
Brandon Rogers Yakama Confederated Tribes Yes Supervisor rogb@yakamafish-nsn.gov (509) 949-4109
Christopher Roper Bonneville Power Administration No Interested Party cproper@bpa.gov (503) 230-3514
Hans Smith Yakama Confederated Tribes Yes Contract Manager h.smith@methownet.com (509) 449-2750


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All administrative tasks fulfilled with timely quality products B: 119. Perform project management and administrative duties 12/31/2019
USFS Environmental Compliance on Yakama Nation Fisheries Projects (BPA's EC covered in REL 161) D: 165. FY 19 USFS NEPA 2017-164 (BPA's EC covered in REL 161) 12/31/2019 12/31/2019
Final Restoration Plan for Stormy A Project Site E: 175. Stormy Area A - USFS Re-Design 2014-125 12/31/2019 07/01/2019
Construction Management F: 100. Stormy Area A - USFS Construction Management 2014-125 12/31/2019 09/16/2019
Stormy A Restoration G: 29. Stormy Area A - USFS Construction 2014-125 12/31/2019 08/17/2019
Concept Level Designs and Report for Leavenworth Area Project H: 175. Leavenworth Area Design 2017-185 12/31/2019
Lower Wenatchee Reach 3 Concept Level Restoration Plan I: 175. Lower Wenatchee River Reach 3 Design 2017-186 12/31/2019
Skinney Creek Finalized Restoration Plan J: 175. Skinney Creek Design 2015-144 12/31/2019
Chiwawa Fan Finalized Restoration Plan K: 175. Chiwawa Fan - Design 2016-165 12/31/2019
Nason Confluence Finalized Restoration Plan L: 175. Nason Confluence - Design 2013-105 12/31/2019 12/31/2019
Nason Creek N1 DOT Concept Level Restoration Plan M: 175. Nason Creek N1 DOT Design 2018-198 12/31/2019 12/31/2019
Final Restoration Plan for Chewuch RM 4.6 N: 175. Chewuch RM 4.6 Design 2017-176 12/31/2019 12/31/2019
Conceptual Restoration Plan for the Chewuch Floodplain Ranch Project O: 175. Chewuch Floodplain Ranch Design 2019-202 12/31/2019 12/31/2019
Updated Barrier Removal Designs and Report P: 175. Eight Mile Barrier Removal Design 2015-141 12/31/2019
Finalized Restoration Plan, Construction Oversight and Develop Monitoring Plan Q: 175. Beaver Creek Reach 5 - Design 2017-171 12/31/2019 12/18/2019
Construction Management R: 100. Beaver Creek Reach 5 - Construction Oversight 2017-171 12/31/2019 09/30/2019
Beaver Creek Reach 5 Restoration S: 29. Beaver Creek Reach 5 Construction 2017-171 12/31/2019 09/19/2019
Finalize Restoration Plan for the Fawn Creek Project Area T: 175. Fawn Creek Project - Design 2015-147 12/31/2019
Finalize Restoration Plan for the Twisp River War Creek Project U: 175. Twisp River - War Creek Area Restoration Design 2015-148 12/31/2019
Finalized Restoration Plan for Twisp Horseshoe USFS Lands V: 175. Twisp Horseshoe Phase 2 (USFS) Restoration Engineering 2010-39 12/31/2019
Confidential Water Rights Evaluation W: 154. Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 12/31/2019
Alternative Water Delivery Feasibility Assessment X: 175. Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152 12/31/2019
Finalized Restoration Plan for the Alder Creek Floodplain Y: 175. M2 Alder Creek Floodplain Design 2019-201 12/31/2019
Partial completion of BPA's land acquisition process Z: 172. Western Rivers Methow Acquisition Support 2018-200 12/31/2019
Wolf Creek Reach Assessment Report AA: 115. New CCR 41925 - Wolf Creek Reach Assessment 2019-206 12/31/2019
Permit Level Restoration Plan for the Deadhorse Project Area AB: 175. New CCR 41925 - Upper Wenatchee Deadhorse Tunnel Design 2012-103 12/31/2019
Conceptual Restoration Plan for the Chiwawa River Outlet Project Area AC: 175. New CCR 41925 - Chiwawa Outlet Conceptual Design 2019-205 12/31/2019
Permit and Construction Level Restoration Plans for the Upper Twisp Project Area AD: 175. New CCR 41925 - Upper Twisp River and Tributaries Project Design (USFS Projects) 2016-162 12/31/2019
Permit and Construction Level Restoration Plans for the Little Bridge Creek Project Area AE: 175. New CCR 41925 - Little Bridge Creek Design (USFS Projects) 2017-182 12/31/2019
Construction Management Complete AF: 100. New CCR 41925 - Nason Upper Kahler Construction Oversight 2017-166 12/31/2019
Permit and Construction Level Restoration Plans for the Upper Stillwaters Project Area AG: 175. New CCR 41925 - Entiat Upper Stillwaters USFS Design 2017-167 12/31/2019
Fish Passage Technical Memo AH: 115. New CCR 41925 - Nason Creek Anadromous Barrier Assessment 2019-207 12/31/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 20 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 100 Construction Management
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 19 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 3 instances of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2018
B 119 Perform project management and administrative duties 10/01/2018
C 132 (No annual report required for this contract) 10/01/2018
D 165 FY 19 USFS NEPA 2017-164 (BPA's EC covered in REL 161) 10/01/2018
E 175 Stormy Area A - USFS Re-Design 2014-125 10/01/2018
F 100 Stormy Area A - USFS Construction Management 2014-125 10/01/2018
G 29 Stormy Area A - USFS Construction 2014-125
H 175 Leavenworth Area Design 2017-185 10/01/2018
I 175 Lower Wenatchee River Reach 3 Design 2017-186 10/01/2018
J 175 Skinney Creek Design 2015-144 10/01/2018
K 175 Chiwawa Fan - Design 2016-165 10/01/2018
L 175 Nason Confluence - Design 2013-105 10/01/2018
M 175 Nason Creek N1 DOT Design 2018-198 10/01/2018
N 175 Chewuch RM 4.6 Design 2017-176 10/01/2018
O 175 Chewuch Floodplain Ranch Design 2019-202 10/01/2018
P 175 Eight Mile Barrier Removal Design 2015-141 10/01/2018
Q 175 Beaver Creek Reach 5 - Design 2017-171 10/01/2018
R 100 Beaver Creek Reach 5 - Construction Oversight 2017-171 10/01/2018
S 29 Beaver Creek Reach 5 Construction 2017-171 08/01/2019
T 175 Fawn Creek Project - Design 2015-147 10/01/2018
U 175 Twisp River - War Creek Area Restoration Design 2015-148 10/01/2018
V 175 Twisp Horseshoe Phase 2 (USFS) Restoration Engineering 2010-39 10/01/2018
W 154 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 10/01/2018
X 175 Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152 10/01/2018
Y 175 M2 Alder Creek Floodplain Design 2019-201 10/01/2018
Z 172 Western Rivers Methow Acquisition Support 2018-200 10/01/2018
AA 115 New CCR 41925 - Wolf Creek Reach Assessment 2019-206 10/01/2018
AB 175 New CCR 41925 - Upper Wenatchee Deadhorse Tunnel Design 2012-103 10/01/2018
AC 175 New CCR 41925 - Chiwawa Outlet Conceptual Design 2019-205 10/01/2018
AD 175 New CCR 41925 - Upper Twisp River and Tributaries Project Design (USFS Projects) 2016-162 10/01/2018
AE 175 New CCR 41925 - Little Bridge Creek Design (USFS Projects) 2017-182 10/01/2018
AF 100 New CCR 41925 - Nason Upper Kahler Construction Oversight 2017-166
AG 175 New CCR 41925 - Entiat Upper Stillwaters USFS Design 2017-167 10/01/2018
AH 115 New CCR 41925 - Nason Creek Anadromous Barrier Assessment 2019-207 10/01/2018